The drywall was hung in just one day!
< 2/13/05 > |
 |
 |
< Drywall finishing started
2/19/05. It was more or less completed in record time 2/22 at
5 pm. We painted all night so we didn't have to reschedule the
carpet installation.
Cabinets arrive 2/21/05 > |
 |
 |
< Carpet arrived 2/23.
Some furniture (the rest will be early April)
arrived 2/24. Cheech christened the new white upholstery and
we had Champagne, a glass for each of us and one for the carpet.
> |
 |
 |
< Cabinet installation was completed 2/25 just before
the appliances arrived.
Wiring and plumbing were almost complete the same
night. > |
 |
|
Part of each room is civilized -- the other
part is a construction zone. |
 |
 |
At least, we can eat, sit, sleep |
 |
 |
and best of all,
SEE OUT! |
 |
As of March 20, we are more or less finished upstairs until the
rest of our furniture and drapes arrive. The ground floor is
now high priority. Dry wall repair, painting and new carpet are
in the works. |